pisco_log
banner

Applied Research on Software Progress Measurement: Taking B2B Project of A Company as an Example

Shuangxi Zhang, Norriza Hussin

Abstract


Because of the limitations of Earned Value Management (EVM), there are great defects in managing software progress. Although Earned Schedule (ES) improves EVM, it is not reliable to utilize cost data to measure software progress. In 2014, Earned Duration Management (EDM), which is a new measurement method, was introduced. In this paper, via a practical case, the EDM method is used to measure the software progress.


Keywords


Software Progress; Earned Value Management; Earned Duration Management; Schedule Performance Index (SPI); Duration Performance Index (DPI)

Full Text:

PDF

Included Database


References


Anbari FT. The earned schedule. PMI® Research and Education Conference; 2012 July 18.

Khamooshi H, Golafshani H. EDM: Earned Duration Management, a new approach to schedule performance management and measurement. International Journal of Project Management; 2014; 32(6): 1019–1041.

PMI. Practice standard for earned value management. PM, March-April. 2011.

PMBOK. PMBOK guide (6th Edition). In Project Management Institute; 2017.

Vanhoucke M, Andrade P, Salvaterra F, et al. Introduction to earned duration. The Quartely Magazine of the College of Performance Management 2015.




DOI: http://dx.doi.org/10.18282/bam.v2i1.1081

Refbacks

  • There are currently no refbacks.